Service Outage - We are currently experiencing a service outage related to a fire at 7–9 Fanshawe Street, Auckland CBD. Please view our status page for more information. Click here →
Network status
Partial outage · Restoration in progress

Partial outage: Auckland CBD (7 Fanshawe Street)

A fire in the basement of 7 Fanshawe Street has damaged one of our key CBD network sites. Some internet and data services are down. Restoration is in progress.
Incident INC0262691 · Last updated Tuesday 24 November 2026, 8:30am NZDT · Next update 4:30pm today
27%of affected services restored
Days, not hours
Expect a multi-day recovery. Services are coming back in stages as each new fibre path is completed and tested. We are not able to give a single restore time for all services. Services that connect to equipment inside the building will take longest.

Current status

  • Core network routes (two priority routes)Restored
  • Street bypass and fibre splicingIn progress
  • Rerouting, configuration changes and migrationsIn progress
  • Service verificationIn progress
  • Site powerRunning on generator
  • Site coolingTemporary cooling running

Affected services by recovery path (as at 22 November)

46%
Need new fibre. Being restored through street bypass and splicing.
43%
Need power. A fibre path is likely available once building power returns.
11%
Need both power and new fibre.
Working estimates, subject to change as each service is checked. Restoration is confirmed by our Network Operations Centre.

Updates

  1. Tuesday 24 November 2026, 8:30am NZDT

    Latest UpdateCBD PoP fire: recovery update

    Where we are

    • Generator power has run the CBD PoP since late yesterday afternoon. Power held overnight.
    • The permanent air-conditioning was damaged in the fire and is out of service. Temporary cooling is running. We are bringing equipment back online only within safe temperature limits.
    • 27% of affected services are restored.
    • Fibre splicing and rerouting are continuing, along with configuration changes, migrations and service verification.

    P1 and high-priority requests

    We have not answered your P1 and high-priority requests as fast as we should have. That changes today.
    Every P1 request will get a written response by COB today. Each response will cover:
    • the current state of your service
    • what its recovery depends on
    • your restoration or workaround options
    For each service we will look at every recovery path:
    • fibre restoration or rerouting
    • power-led recovery
    • combined power and fibre restoration
    • logical configuration changes and migrations
    • a rebuild in another facility or on another service
    Once your service has been assessed, the NOC will contact you directly.

    What we don't know yet

    • When permanent cooling will be repaired or replaced. We expect to know this morning.

    Next update

    4:30pm today, Tuesday 24 November 2026.

    Urgent questions

    Please contact the NOC directly at noc@vector.co.nz. Please quote your service ID.
  2. Monday 23 November 2026, 13:00

    UpdateCustomer update

    There has been no significant change to the overall incident position since our previous update. Recovery activity continues across all areas of the restoration plan.
    Field crews remain engaged in fibre splicing and rerouting activity. Following completion of the most concentrated splicing activity over the weekend, the remaining work is more distributed and service-specific. As a result, the restoration run rate has slowed somewhat as teams work through these more targeted fibre requirements.
    In parallel, our network and engineering teams continue progressing service rebuild options through alternative Vector Fibre facilities, including logical configuration and migration opportunities where technically viable.
    A significant focus this morning has been on building access and the associated governance requirements. Engagement continues with site control, building management and building ownership as we work to establish the safest and quickest pathway to progress the infrastructure and power-dependent elements of the recovery.
    We are also continuing to develop greater service-level visibility across the three recovery pathways, with the aim of providing customers with clearer information on what has been restored, what remains outstanding and the dependencies affecting different groups of services.
    Our NOC will continue to contact customers directly as service-specific information becomes available. Customers with high-priority affected services, or who believe a viable alternative configuration or migration may be available, are encouraged to engage with our NOC or their Vector Fibre KAM for review.
  3. 22 November 2026

    UpdateField recovery and building position

    • Fibre splicing in street-side pits to bypass the building is under way. Some services in this group are restored.
    • Additional field crews are being onboarded. The rate of work is increasing.
    • The building has been formally notified as unsafe. The building owner must complete remediation before access and power can be restored.
    • We have proposed a temporary cable route into Level 1 of the building. This needs safety approval before it can go ahead.
    • Our network team is assessing which services can be moved to alternate paths, and migrating them where it is safe to do so.
  4. 21 November 2026

    UpdateTwo core routes restored

    • Two priority core network routes have been restored.
    • Planning and preparation for the first fibre splicing work is complete.
    • No further building access is permitted until additional structural assessment is complete.
  5. Earlier

    IdentifiedDamage assessed

    • A supervised safety assessment confirmed extensive damage to fibre cables from the building entry point through the basement.
    • Structural damage to beams and columns was identified.

Contact

About your service: Contact your internet or data service provider first. They can see your connection and will work with us.
Vector Fibre Network Operations Centre: noc@vector.co.nz For urgent questions, contact the NOC directly. Please quote your service ID.
Health, safety or emergency service impacts: Tell your provider or email noc@vector.co.nz straight away so it can be prioritised.